Waterbury Roadway Milling and Paving Program Schedule
(WATERBURY, CT)
The City of Waterbury Engineering Department is announcing the approximate
milling and paving schedule for this week and next, weather dependent.
The public can anticipate delays and/or detours and may
want to consider alternate routes. Parking on the streets will be prohibited
during working hours, which are from 7 a.m. to 6 p.m.
Milling and Paving Schedule:
Wednesday, October 7
Frost Road: Concrete ramp installation
Plank Road: Milling
Thursday, October 8
Frost Road: Concrete ramp installation
Plank Road, Luke Street, Keefe Street and Fairmount Street: Milling
Friday, October 9
Frost Road: Concrete ramp installation
Luke Street, Keefe Street, Fairmount Street and Sharon Road: Milling
Saturday, October 10
Frost Road: Concrete ramp installation
Monday, October 12
Frost Road: Concrete ramp installation
Franklin Street, Pond Street, Denny Street and Sharon Road: Milling
Tuesday, October 13
Frost Road: Concrete ramp installation
Sharon Road, Boland Drive, Windy Drive and Windy Drive Extension: Milling
Wednesday, October 14
Woodtick Road: Concrete ramp installation
Windy Drive, Blue Trail Drive and Ferrone Avenue: Milling
Thursday, October 15
Woodtick Road: Concrete ramp installation
Ferrone Avenue and Pearl Lake Road: Milling
Friday, October 16
Woodtick Road: Concrete ramp installation
Pearl Lake Road: Milling
Saturday, October 17
Woodtick Road: Concrete ramp installation
Denny Street, Franklin Street, Pond Street, Luke Street, Keefe Street and
Fairmount Street: Paving
The Engineering Department may be contacted at 203-574-6851