Press
Release
For
Immediate Release
January
7, 2026
Contact:
Jennifer
Rose
Press
Secretary, Office of Mayor Paul K. Pernerewski, Jr.
Email:
Jrose@waterburyct.org
City
of Waterbury Provides Update on Thomaston Avenue Water Main Break and 42-Inch
Sliplining Project
(Waterbury,
CT) The City of Waterbury is providing an update on the water main break
repairs on Thomaston Avenue and the ongoing 42-inch sliplining project, both of
which are nearing completion.
Water
Main Break Repairs
All
pipe work in the ground associated with the water main break has been
successfully replaced, pressure tested, and is now operationally available. The
temporary bypass has been removed from the 36-inch low service main, and full
volume and pressure are currently flowing to the city.
The
36-inch high pressure main has been pressure tested and disinfected, with
acceptable results. This line will be opened to the 42-inch main once that work
is completed later this week. Repairs to the 12-inch line have also been
pressure tested without issue.
The
roadway has been fully backfilled and is awaiting final paving, which is
anticipated to occur next week once the asphalt plant reopens.
Mayor
Paul K. Pernerewski, Jr. praised the collective effort involved in restoring
the system.
This
was a complex failure affecting some of the most critical water infrastructure
in our city, and the progress made in a short period of time is a direct result
of the tireless work of our crews and contractors, said Mayor Pernerewski. I
am grateful to everyone who worked around the clock in extremely difficult
conditions, and I want to thank our residents and business owners for their
patience and cooperation throughout this process.
42-Inch
Sliplining Project
Pressure
testing of the 42-inch sliplining project is underway today. While crews
encountered issues yesterday with several mechanical connections, those
problems have been resolved and the pipe is currently holding pressure. The
line must maintain pressure for a full 24-hour period before it can be approved
for operational use.
Once
pressure testing is successfully completed, Murphy Pipeline will begin
backfilling and closing the nine pits located between Waterville Park and the
start of the project further down Thomaston Avenue
Because
the 42-inch main has been out of service for nearly nine months, the pipe must
undergo a required disinfection period of 24-hours followed by bacteriological
sampling. Once all samples are confirmed clear, the 42-inch main will be placed
back into service, allowing water to flow again from the treatment plant and
through the repaired 36-inch high service main.
Bradley
Malay, Superintendent of Water, emphasized the importance of the final testing
and restoration steps.
Every
component of this system has now been repaired and tested, and we are moving
through the final validation process, said Malay. Holding pressure,
completing disinfection, and confirming bacteriological results are critical
steps to ensure long term reliability and water quality before the system is
fully returned to service.
Once
the 42-inch main is operational, the city will be fully functional and largely
redundant, significantly strengthening Waterbury s ability to respond to any
future water main issues.
Next
Steps
With
the emergency repairs and restoration work nearing completion, the city will
now begin evaluating and advancing a plan for critical valve replacements
within the water system. These improvements are intended to better isolate
sections of the system in the event of future failures, reducing service
impacts and improving overall system resiliency.
Mayor
Pernerewski noted that the recent incident underscores the importance of
continued investment in core infrastructure.
As
we move out of response mode and back into normal operations, this is the right
time to take a hard look at system upgrades that will strengthen our ability to
isolate and respond to future issues, said Mayor Pernerewski. This event has
reinforced the need to keep investing in the reliability and resilience of
Waterbury s water system.
Additional
updates will be provided as final testing and restoration activities are
completed.