6/12/2025 - PRESS RELEASE Waterbury Milling Schedule for June 12- June 20

 

2025 Waterbury Roadway Milling Program Schedule

Press Release

 

For Immediate Release

 

 

 

The City of Waterbury Engineering Department is pleased to announce the approximate milling and paving, schedule for this week and next, weather dependent. The public can anticipate delays and/or detours and may want to consider alternate routes. Parking on the streets will be prohibited during working hours, which extend from 7 a.m. to 6 p.m.

 

Milling

         Harker Ave, North Harker Ave, Erma Drive: June 12, 2025 June 13, 2025

         Bond Street, Villa Road, Emmet Ct, Washington St, Kenyon St, Laurel St, and Taylor Road: June 16, 2025 June 17, 2025

         Birchwood St, Greenbow St, and Cynthia St: June 18, 2025

 

Paving

         Start paving on Chipper Road: June 13, 2025

         Chipper Road, Blue Ridge Drive and start Starlet Lane: June 16, 2025

         Starlet Lane, Holiday Hill Road, Carnation Drive, Valentino Drive, Dan Parker, Blueberry Hill, Catalina Drive, and Melody Lane: June 17, 2025 June 20, 2025

 

 

The Engineering Department may be contacted at 203-574-6851 if anyone has questions regarding this program.

 

 