2025 Waterbury Roadway Milling Program Schedule
Press Release
For Immediate Release
The City of
Waterbury Engineering Department is pleased to announce the approximate milling
and paving, schedule for this week and next, weather dependent. The public can
anticipate delays and/or detours and may want to consider alternate routes.
Parking on the streets will be prohibited during working hours, which extend
from 7 a.m. to 6 p.m.
Milling
Harker Ave, North Harker Ave, Erma Drive: June 12, 2025 June
13, 2025
Bond Street, Villa Road, Emmet Ct, Washington St, Kenyon St,
Laurel St, and Taylor Road: June 16, 2025 June 17, 2025
Birchwood St, Greenbow St, and Cynthia St: June 18, 2025
Paving
Start paving on Chipper Road: June 13, 2025
Chipper Road, Blue Ridge Drive and start Starlet Lane: June 16,
2025
Starlet Lane, Holiday Hill Road, Carnation Drive, Valentino
Drive, Dan Parker, Blueberry Hill, Catalina Drive, and Melody Lane: June 17,
2025 June 20, 2025
The Engineering Department may be
contacted at 203-574-6851 if anyone has questions regarding this program.