11/1/2005 - Updated Paving Schedule For 10/6-10/8 2005

Updated Paving Schedule

The City of Waterbury is continuing with their paving program as scheduled. The milling portion and paving portion of the paving program has been ongoing for the past week. As in both cases,” No Parking” signs are and will be posted twenty-four hours in advance of work being done. All residents and business establishments are asked to comply with these directives. Failure to do so will result in vehicles being towed.

Schedule for 11/01/05 through 11/05/05 is as follows, weather permitting:

Paving :

     Finish North Walnut St., proceed to Wood St.

     Oak St., Finish Walnut St. and Welton St.

After these Streets are completed, crews will move to:

 Wheeler St., Boyden St., Bucks Hill Rd., Rosengarten, and Chestnut.

All of the above work is dependant upon weather cooperation and

Contractor availability.

In the event of inclement weather, schedules will be backed up for the appropriate time frame. Schedules will be updated as work progresses.