The 2016 milling and paving program began Monday Sept.
26. Work will begin in the Cooke Street area including Greenwood Avenue,
Melbourne Terrace, White Street, Bonair Avenue and Lone Oak Avenue. Crews will
begin installing ADA pedestrian ramps at required intersections followed by the
milling and paving crews.
All affected streets will be posted with “No Parking” signs
in advance of the work. Residents must adhere to the No Parking requirement in
order to avoid the towing of vehicles. Motorists are urged to exercise caution
in these work areas, due to equipment and workers in the work zones.
Any question regarding the paving program can be addressed
to the Public Works Department, Bureau of Engineering at (203) 574-6851
The paving program will continue for approximately four
weeks, weather permitting, and the sequence of streets is below:
Greenwood Avenue
Cooke Street
Melbourne Terrace
White Street
Bonair Avenue
Lone Oak Avenue
North Main Street from Bucks Hill Road to Boyden Street
Extension
Farmwood Road
North Walnut Street
Rhode Island Avenue
Massachusetts Avenue
Melrose Street
Rosedale Avenue
Greenleaf Avenue
Cottage Place
Printers Court
State Street
Country Club Road
East Ridge Drive
West Ridge Drive
South Ridge Drive
White Birch Dr
Ardsley Road
Madeline Avenue
Mildred Avenue
Belmont Drive
Armand Drive
Kaynor Drive